Â鶹´«Ã½Ó³»­

Skip to content
Join our Newsletter

First Quantum suspends ore processing at Cobre Panama as dispute escalates

TORONTO — First Quantum Minerals Ltd. has suspended ore processing operations at its Cobre Panama mine. The stoppage is the latest escalation in its dispute with the Panamanian government over tax and royalty payments.
2023022308024-63f7648bb2e2c287f36c97bbjpeg
The open pit copper mine Cobre Panama, run by Panamanian Mining company Minera Panama, a subsidiary of Canada's First Quantum Minerals Ltd., stands in Donoso, Panama, Dec. 6, 2022. First Quantum Minerals Ltd. has suspended ore processing operations at its Cobre Panama mine. THE CANADIAN PRESS/AP-Abraham Teran

TORONTO — First Quantum Minerals Ltd. has suspended ore processing operations at its Cobre Panama mine.

The stoppage is the latest escalation in its dispute with the Panamanian government over tax and royalty payments.

The Toronto-based company says the interruption is due to Panamá Maritime Authority’s refusal to permit copper concentrate loading operations at the mine’s port.

First Quantum says it will begin a partial demobilization of its workforce of over 8,000 employees and contractors due to the stoppage.

The government in Panama ordered the suspension of work at the mine in December after the two sides failed to reach a new profit-sharing agreement.

First Quantum says negotiations with the government on a new contract are continuing.

This report by The Canadian Press was first published Feb. 23, 2023.

Companies in this story: (TSX:FM)

The Canadian Press